Brunswick Park Friday 16th April 2021 15:40:00


We are currently aware of the outage affecting the site at the moment. We have asked the building management to reset the power once again.

We have planned works on Tuesday to resolve the electrical issue which is the underlaying cause. More information will be communicated shortly.

Our engineers restored service at approximately midnight. The temporary service link will stay in place until planned works are announced and scheduled.

We will continue to monitor the services over the course of the early hours to ensure stability has returned.

Since the latest electrical outage the equipment has failed. Our engineers are on route to replace the equipment servicing the building.

Engineers are scheduled to arrive approx. 8PM.

An update will be posted upon their arrival.

Engineers have arrived at 8:30pm. Equipment is currently being replaced with a temporary link to provide stability until the planned works within the building can take place.